Sydney Olympic Park Aquatic Centre (SOPAC)

Sydney Olympic Park Aquatic Centre (SOPAC) CPB Contractors (formerly Leighton Contractors) was selected by the Olympic Coordination Authority to deliver the Sydney Olympic Park Aquatic Centre (SOPAC) expansion in Homebush Bay, NSW, under a construction contract.

The project involved increasing the spectator capacity of the existing Aquatic Centre from 5,500 to 17,500 seats for the Olympic Games, with a post-Games reconfiguration to 8,000 seats. The works were delivered between June 1999 and July 2001, under a demanding schedule to ensure Olympic preparations were not compromised.

Prestressed precast concrete seating platforms supported by heavy structural steel raking beams Tubular steel roof trusses providing full-width column-free spans of over 100 metres Hollow-core precast concrete planks forming the upper concourse level Metal deck roofing and recyclable cladding to temporary wall ends Air conditioning systems servicing the fully enclosed building Seating for 12,000 patrons, five scoreboards, and two video screens

The Aquatic Centre remained open to the public throughout construction, including during the removal of the eastern façade Dust and noise levels were closely monitored to minimise disruption CPB Contractors proposed an alternative design concept during competitive tendering, delivering significant cost savings A $6 million variation was agreed to dismantle much of the temporary structure and adjust seating to its permanent configuration

In support of Environmentally Sustainable Development (ESD), CPB negotiated an agreement with the Wollongong Sportsground Trust to re-use 90% of dismantled components in the construction of a new grandstand at WIN Stadium, Wollongong.

Construction was completed ahead of schedule, delivering a world-class facility that supported the success of the Sydney 2000 Olympic Games.

Latest news and updates 17 August 2026 Piling commences on new Bundaberg Hospital project Piling works have officially commenced on the new Bundaberg Hospital, marking a significant milestone in the delivery of one of Queensland's largest health infrastructure projects. 13 August 2026 Engineering innovation delivering better environmental outcomes in Tasmania At the Ti Tree Bend Sewage Treatment Plant in Launceston, innovation isn’t just about building new sewerage infrastructure - it’s about rethinking how it’s designed, delivered and integrated to achieve better outcomes for Tasmanian communities and environment. 12 August 2026 CPB Contractors welcomes future industry leaders to Cross River Rail CPB Contractors, in partnership with Transport Australia, welcomed more than 50 engineers at the association’s Emerging Leaders Forum in Brisbane last week, providing the next generation of infrastructure professionals with a unique opportunity to hear firsthand about the delivery of Cross River Rail and the lasting legacy it will leave for Queensland. 11 August 2026 Collaboration Delivers Smarter Solutions for Complex Foundation Challenges CPB Contractors Engineering Manager Gerard Quigg and Project Manager Dobu Unugueanu recently presented a technical paper at the 2026 joint conference of the Deep Foundation Institute (DFI) and the piling Foundation Specialists Federation (PFSF) in Sydney, showcasing how collaboration across the CIMIC Group can help solve complex engineering challenges. 09 August 2026 Completion of Western Sydney International Airport's Stage 1 Cargo Works Practical completion has been achieved on Stage 1 Cargo Works at Western Sydney International (Nancy-Bird Walton) Airport (WSI), marking a significant milestone in the delivery of Sydney’s new 24-hour global gateway. 04 August 2026 Building futures through CareerTrackers Remy Ryalls journey CPB Contractors' partnership with CareerTrackers is building capability, confidence and long-term careers for Aboriginal and Torres Strait Islander students. As we celebrate NAIDOC Week and this year's theme, '50 Years of Deadly', we're recognising the next generation of Indigenous professionals helping shape Australia's future. Undergraduate Engineer Remy Ryall is one of those future leaders. 26 July 2026 Powering the Future: Electrification Driving Sustainability on Suburban Rail Loop East Our Suburban Connect team is advancing sustainable construction practices across the Suburban Rail Loop East project through a growing suite of electrification and renewable energy initiatives. 23 July 2026 Powering the Future: Electrification Driving Sustainability on Suburban Rail Loop East Our Suburban Connect team is advancing sustainable construction practices across the Suburban Rail Loop East project through a growing suite of electrification and renewable energy initiatives. 21 July 2026 CIMIC's UGL and CPB Contractors to build Neoen's Narrogin Wind Farm with Envision Energy UGL and CPB Contractors have been selected by Neoen and Envision to construct Neoen’s 179 MW Narrogin Wind Farm in Western Australia, a project that supports the state’s energy transition and growing demand for reliable, lower-emissions power. 17 July 2026 Milestone moment for new Dunedin Hospital Vertical construction is now underway on the New Dunedin Hospital | Project Whakatuputupu Inpatient Building, with the first structural steel installed on Wednesday, marking the start of the inpatient building rising above ground. Next

Piling commences on new Bundaberg Hospital project
Engineering innovation delivering better environmental outcomes in Tasmania